Project Start Date: Tue 6/25/02 8:00 AM
Project Finish Date: Mon 8/5/02 10:00 PM
Resources and Assignments | Start | Finish | Work |
---|---|---|---|
Unassigned | Fri 7/5/02 5:00 PM | Mon 8/5/02 10:00 PM | 0 hrs |
Ready for beam Phase III | Mon 8/5/02 10:00 PM | Mon 8/5/02 10:00 PM | 0 hrs |
Approval process complete | Tue 7/23/02 5:00 PM | Tue 7/23/02 5:00 PM | 0 hrs |
Steel and Support Structure ready | Fri 7/5/02 5:00 PM | Fri 7/5/02 5:00 PM | 0 hrs |
Make interface sheets | Wed 7/17/02 8:00 AM | Mon 7/22/02 5:00 PM | 0 hrs |
Hardware installed--check with Lee Hammond | Mon 7/8/02 8:00 AM | Fri 7/12/02 5:00 PM | 0 hrs |
Hardware wired and tested | Sat 7/13/02 8:00 AM | Thu 7/18/02 5:00 PM | 0 hrs |
Monitor ready for phase III | Thu 7/25/02 11:30 AM | Thu 7/25/02 11:30 AM | 0 hrs |
Hiep's Group | Wed 7/10/02 1:00 PM | Mon 8/5/02 11:00 AM | 868 hrs |
Remove BPMs and multiwires in horn cavity | Wed 7/10/02 3:00 PM | Wed 7/10/02 4:30 PM | 12 hrs |
Remove triplet quads | Wed 7/10/02 1:00 PM | Wed 7/10/02 3:00 PM | 16 hrs |
Install trolley rail system & trolley | Thu 7/11/02 1:00 PM | Thu 7/11/02 4:00 PM | 24 hrs |
Bring and align coffins | Fri 7/12/02 1:00 PM | Sat 7/13/02 8:00 AM | 32 hrs |
Install horn module & remove coffins | Sat 7/13/02 8:00 AM | Mon 7/15/02 8:00 AM | 64 hrs |
Add air barrier, angles on horn module | Mon 7/15/02 8:00 AM | Mon 7/15/02 12:00 PM | 32 hrs |
Install RAW piping connections | Tue 7/16/02 1:00 PM | Wed 7/17/02 8:00 AM | 32 hrs |
Setup rail structure for target & BPM modules | Wed 7/17/02 8:00 AM | Wed 7/17/02 12:00 PM | 32 hrs |
Install target module in horn box | Thu 7/18/02 7:30 AM | Thu 7/18/02 11:30 AM | 32 hrs |
Install BPM module, plug in cables | Thu 7/18/02 11:30 AM | Thu 7/18/02 4:30 PM | 32 hrs |
Install target cooling systems racks | Fri 7/19/02 7:30 AM | Fri 7/19/02 11:30 AM | 32 hrs |
Install piping, target cooling system to target module | Fri 7/19/02 11:30 AM | Mon 7/22/02 11:30 AM | 128 hrs |
Remove target cooling piping & BPM cable conn. | Tue 7/23/02 7:30 AM | Tue 7/23/02 11:30 AM | 32 hrs |
Remove BPM module and Thomson rail structure | Tue 7/23/02 11:30 AM | Tue 7/23/02 2:30 PM | 16 hrs |
Setup target coffin support structure, coffin | Tue 7/23/02 2:30 PM | Tue 7/23/02 4:30 PM | 16 hrs |
Remove target module, pulling into coffin | Wed 7/24/02 7:30 AM | Wed 7/24/02 11:30 AM | 32 hrs |
Remove Coffin and extract target module from coffin | Wed 7/24/02 11:30 AM | Wed 7/24/02 2:30 PM | 16 hrs |
Setup rail structure for target & BPM modules | Wed 7/24/02 2:30 PM | Wed 7/24/02 4:30 PM | 16 hrs |
Install target module into horn box | Thu 7/25/02 11:30 AM | Thu 7/25/02 2:30 PM | 16 hrs |
Install BPM module | Thu 7/25/02 2:30 PM | Thu 7/25/02 4:30 PM | 16 hrs |
Connect BPM cables, install target cooling piping | Fri 7/26/02 7:30 AM | Fri 7/26/02 9:30 AM | 16 hrs |
Remove Thomson rail structure, trolley and rails | Fri 7/26/02 9:30 AM | Fri 7/26/02 11:30 AM | 16 hrs |
Install Striplines | Fri 7/26/02 11:30 AM | Sat 7/27/02 11:30 AM | 64 hrs |
Install air barrier interface around horn module | Mon 7/29/02 11:00 AM | Tue 7/30/02 11:00 AM | 56 hrs |
Install triplet quads | Mon 7/29/02 11:00 AM | Tue 7/30/02 11:00 AM | 8 hrs |
Install Herculite air barrier between rows 4 & 5 | Sat 8/3/02 4:00 PM | Mon 8/5/02 11:00 AM | 32 hrs |
Transport triplet quads and stands to MI-60 | Thu 7/11/02 8:00 AM | Thu 7/11/02 12:00 PM | 32 hrs |
Assemble monitor on target | Mon 7/22/02 11:30 AM | Mon 7/22/02 4:30 PM | 8 hrs |
Route cables on target module | Thu 7/25/02 7:30 AM | Thu 7/25/02 11:30 AM | 8 hrs |
Horn Physicists | Sat 7/27/02 11:30 AM | Mon 7/29/02 11:00 AM | 31 hrs |
Checkout horn cooling system | Sat 7/27/02 11:30 AM | Sat 7/27/02 2:00 PM | 3 hrs |
Checkout target cooling system | Sat 7/27/02 2:00 PM | Sat 7/27/02 3:30 PM | 3 hrs |
Checkout Horn Electrical System | Sat 7/27/02 3:30 PM | Sat 7/27/02 5:00 PM | 3 hrs |
Checkout Target Instrumentation | Sun 7/28/02 8:00 AM | Sun 7/28/02 9:30 AM | 3 hrs |
Horn on/off test for electrical noise on instrumentation tests | Sun 7/28/02 9:30 AM | Sun 7/28/02 11:00 AM | 3 hrs |
Horn Pulse Testing | Sun 7/28/02 11:00 AM | Mon 7/29/02 11:00 AM | 16 hrs |
Riggers | Fri 7/5/02 1:00 PM | Mon 8/5/02 8:00 PM | 287.5 hrs |
Remove 3 rows of blocks | Tue 7/9/02 3:30 PM | Tue 7/9/02 9:00 PM | 27.5 hrs |
Install four rows of blocks | Fri 8/2/02 11:00 AM | Sat 8/3/02 4:00 PM | 80 hrs |
Install two rows of blocks | Mon 8/5/02 11:00 AM | Mon 8/5/02 8:00 PM | 40 hrs |
Install triplet quads | Mon 7/29/02 11:00 AM | Mon 7/29/02 8:00 PM | 40 hrs |
Cut off 8" on DS end of trolley rails | Fri 7/5/02 1:00 PM | Fri 7/5/02 5:00 PM | 20 hrs |
Concrete block cutting | Mon 7/15/02 5:00 PM | Tue 7/16/02 12:00 PM | 40 hrs |
Setup or cutting | Mon 7/15/02 8:00 AM | Mon 7/15/02 5:00 PM | 40 hrs |
Electrical techs | Wed 7/10/02 11:00 AM | Fri 8/2/02 11:00 AM | 34 hrs |
Disconnect triplet Quads | Wed 7/10/02 11:00 AM | Wed 7/10/02 12:00 PM | 2 hrs |
Connect triplet quads | Wed 7/31/02 11:00 AM | Fri 8/2/02 11:00 AM | 32 hrs |
RFI | Wed 7/10/02 11:00 AM | Fri 8/2/02 11:00 AM | 34 hrs |
Disconnect triplet Quads | Wed 7/10/02 11:00 AM | Wed 7/10/02 12:00 PM | 2 hrs |
Connect triplet quads | Wed 7/31/02 11:00 AM | Fri 8/2/02 11:00 AM | 32 hrs |
Water Techs | Wed 7/10/02 11:00 AM | Fri 8/2/02 11:00 AM | 42 hrs |
Disconnect triplet Quads | Wed 7/10/02 11:00 AM | Wed 7/10/02 12:00 PM | 2 hrs |
Connect triplet quads | Wed 7/31/02 11:00 AM | Fri 8/2/02 11:00 AM | 32 hrs |
Run drain line from enclosure | Fri 7/12/02 10:00 AM | Fri 7/12/02 3:00 PM | 8 hrs |
Vacuum Techs | Wed 7/10/02 11:00 AM | Fri 8/2/02 11:00 AM | 34 hrs |
Disconnect triplet Quads | Wed 7/10/02 11:00 AM | Wed 7/10/02 12:00 PM | 2 hrs |
Connect triplet quads | Wed 7/31/02 11:00 AM | Fri 8/2/02 11:00 AM | 32 hrs |
Alignment Group | Wed 7/10/02 8:00 AM | Wed 7/31/02 12:00 PM | 141 hrs |
"As found" survey of triplet quads | Wed 7/10/02 8:00 AM | Wed 7/10/02 11:00 AM | 9 hrs |
Align Thomson rail structure in line with horn rails | Wed 7/17/02 1:00 PM | Wed 7/17/02 5:00 PM | 12 hrs |
Final align triplet quads | Tue 7/30/02 11:00 AM | Wed 7/31/02 11:00 AM | 24 hrs |
Final Alignment of horn module | Mon 7/15/02 1:00 PM | Tue 7/16/02 12:00 PM | 24 hrs |
Re-align Thomson rails to horn box | Wed 7/24/02 4:30 PM | Thu 7/25/02 11:30 AM | 12 hrs |
Align SWIC | Wed 7/31/02 8:00 AM | Wed 7/31/02 12:00 PM | 12 hrs |
Receiving | Wed 7/10/02 1:00 PM | Tue 7/23/02 4:30 PM | 34 hrs |
Remove triplet quads | Wed 7/10/02 1:00 PM | Wed 7/10/02 3:00 PM | 4 hrs |
Install trolley rail system & trolley | Thu 7/11/02 1:00 PM | Thu 7/11/02 4:00 PM | 6 hrs |
Bring and align coffins | Fri 7/12/02 1:00 PM | Fri 7/12/02 5:00 PM | 8 hrs |
Setup rail structure for target & BPM modules | Wed 7/17/02 8:00 AM | Wed 7/17/02 12:00 PM | 8 hrs |
Setup target coffin support structure, coffin | Tue 7/23/02 2:30 PM | Tue 7/23/02 4:30 PM | 4 hrs |
Transport triplet quads and stands to MI-60 | Thu 7/11/02 8:00 AM | Thu 7/11/02 12:00 PM | 4 hrs |
Operations Group | Thu 6/27/02 1:52 AM | Mon 8/5/02 10:00 PM | 315.63 hrs |
Search and Secure | Mon 8/5/02 8:00 PM | Mon 8/5/02 10:00 PM | 6 hrs |
Test Stability and robustness of autotune to dump | Sat 6/29/02 1:52 PM | Sun 6/30/02 5:52 AM | 16 hrs |
Manual Autotune mode test with offset to dump | Fri 6/28/02 1:52 PM | Sat 6/29/02 1:52 PM | 24 hrs |
Start Autotune studies to determine offset to dump | Fri 6/28/02 1:52 AM | Fri 6/28/02 1:52 PM | 12 hrs |
Signal on 5m muon monitor; lower 25m muon monitor | Thu 6/27/02 1:52 PM | Fri 6/28/02 1:52 AM | 12 hrs |
Target area focussing angle studies with temp. multiwires, short hi intensity tests | Thu 6/27/02 9:52 AM | Thu 6/27/02 1:52 PM | 4 hrs |
Once Tune established; check out eberm, shielding,intensity monitoring | Thu 6/27/02 1:52 AM | Thu 6/27/02 9:52 AM | 8 hrs |
Short High Intensity/low rep rate, loss,aperture,emittance studies | Thu 6/27/02 1:52 AM | Thu 6/27/02 9:52 AM | 8 hrs |
Miscellaneous tuning | Sun 6/30/02 5:52 AM | Tue 7/9/02 3:30 PM | 225.63 hrs |
Welders | Mon 7/15/02 8:00 AM | Mon 7/15/02 12:00 PM | 4 hrs |
Add air barrier, angles on horn module | Mon 7/15/02 8:00 AM | Mon 7/15/02 12:00 PM | 4 hrs |
Safety documentation group | Sat 7/6/02 8:00 AM | Tue 7/16/02 9:00 AM | 73 hrs |
Full statistics Mars calculations due | Mon 7/8/02 8:00 AM | Mon 7/8/02 5:00 PM | 8 hrs |
Comment and rewrite period | Mon 7/8/02 8:00 AM | Wed 7/10/02 5:00 PM | 24 hrs |
Internal exchange of penultimate draft of SA | Sat 7/6/02 8:00 AM | Sat 7/6/02 5:00 PM | 8 hrs |
Update SAD | Fri 7/12/02 9:00 AM | Mon 7/15/02 9:00 AM | 16 hrs |
Turn in to SRC | Fri 7/12/02 8:00 AM | Fri 7/12/02 9:00 AM | 1 hr |
Folder Assembly | Thu 7/11/02 1:00 PM | Thu 7/11/02 5:00 PM | 4 hrs |
Response from SRC, clearance from BD, docs to 7th floor | Mon 7/15/02 9:00 AM | Tue 7/16/02 9:00 AM | 8 hrs |
All documents complete | Thu 7/11/02 8:00 AM | Thu 7/11/02 12:00 PM | 4 hrs |
BD Mech Techs | Mon 7/8/02 8:00 AM | Tue 7/30/02 5:00 PM | 864 hrs |
Steel installed | Tue 7/9/02 8:00 AM | Tue 7/9/02 5:00 PM | 16 hrs |
Support structure installed | Mon 7/8/02 8:00 AM | Mon 7/8/02 5:00 PM | 16 hrs |
Install SWIC | Tue 7/30/02 8:00 AM | Tue 7/30/02 5:00 PM | 16 hrs |
Joel Misek | Mon 7/15/02 8:00 AM | Tue 7/16/02 5:00 PM | 16 hrs |
Sketch parts for Dan Snee | Mon 7/15/02 8:00 AM | Tue 7/16/02 5:00 PM | 16 hrs |
Concrete block cutter | Tue 7/16/02 8:00 AM | Tue 7/16/02 5:00 PM | 8 hrs |
Concrete block cutting | Tue 7/16/02 8:00 AM | Tue 7/16/02 5:00 PM | 8 hrs |
Concrete hole driller | Fri 7/12/02 8:00 AM | Fri 7/12/02 10:00 AM | 2 hrs |
Drill drain hole in enclosure | Fri 7/12/02 8:00 AM | Fri 7/12/02 10:00 AM | 2 hrs |
Salmon Tariq | Thu 7/11/02 2:00 PM | Fri 7/12/02 2:00 PM | 8 hrs |
Design Monitor | Thu 7/11/02 2:00 PM | Fri 7/12/02 2:00 PM | 8 hrs |
Larry Bartoszek | Fri 7/12/02 2:00 PM | Sat 7/13/02 9:00 AM | 4 hrs |
Model monitor in target model | Fri 7/12/02 2:00 PM | Sat 7/13/02 9:00 AM | 4 hrs |
BD drafting | Fri 7/12/02 2:00 PM | Mon 7/15/02 2:00 PM | 8 hrs |
Draft monitor pieces | Fri 7/12/02 2:00 PM | Mon 7/15/02 2:00 PM | 8 hrs |
WHGF shop | Mon 7/15/02 2:00 PM | Fri 7/19/02 2:00 PM | 32 hrs |
Fabricate monitor pieces | Mon 7/15/02 2:00 PM | Fri 7/19/02 2:00 PM | 32 hrs |
Target monitor physicist/EE | Wed 7/17/02 8:00 AM | Fri 7/19/02 5:00 PM | 16 hrs |
Develop read-out for monitor | Wed 7/17/02 8:00 AM | Wed 7/17/02 5:00 PM | 8 hrs |
Software integration into controls | Fri 7/19/02 8:00 AM | Fri 7/19/02 5:00 PM | 8 hrs |
Electricians | Wed 7/17/02 1:00 PM | Mon 7/22/02 12:00 PM | 40 hrs |
Pull cables in MI-12 | Thu 7/18/02 8:00 AM | Thu 7/18/02 5:00 PM | 8 hrs |
Install electr. boxes for target cooling, pull & connect cables | Wed 7/17/02 1:00 PM | Mon 7/22/02 12:00 PM | 32 hrs |