Phase III prep


Project Start Date: Tue 6/25/02 8:00 AM
Project Finish Date: Mon 8/5/02 10:00 PM

Who Does What

Resources and AssignmentsStartFinishWork
Unassigned
Fri 7/5/02 5:00 PMMon 8/5/02 10:00 PM0 hrs
Ready for beam Phase III
Mon 8/5/02 10:00 PMMon 8/5/02 10:00 PM0 hrs
Approval process complete
Tue 7/23/02 5:00 PMTue 7/23/02 5:00 PM0 hrs
Steel and Support Structure ready
Fri 7/5/02 5:00 PMFri 7/5/02 5:00 PM0 hrs
Make interface sheets
Wed 7/17/02 8:00 AMMon 7/22/02 5:00 PM0 hrs
Hardware installed--check with Lee Hammond
Mon 7/8/02 8:00 AMFri 7/12/02 5:00 PM0 hrs
Hardware wired and tested
Sat 7/13/02 8:00 AMThu 7/18/02 5:00 PM0 hrs
Monitor ready for phase III
Thu 7/25/02 11:30 AMThu 7/25/02 11:30 AM0 hrs
Hiep's Group
Wed 7/10/02 1:00 PMMon 8/5/02 11:00 AM868 hrs
Remove BPMs and multiwires in horn cavity
Wed 7/10/02 3:00 PMWed 7/10/02 4:30 PM12 hrs
Remove triplet quads
Wed 7/10/02 1:00 PMWed 7/10/02 3:00 PM16 hrs
Install trolley rail system & trolley
Thu 7/11/02 1:00 PMThu 7/11/02 4:00 PM24 hrs
Bring and align coffins
Fri 7/12/02 1:00 PMSat 7/13/02 8:00 AM32 hrs
Install horn module & remove coffins
Sat 7/13/02 8:00 AMMon 7/15/02 8:00 AM64 hrs
Add air barrier, angles on horn module
Mon 7/15/02 8:00 AMMon 7/15/02 12:00 PM32 hrs
Install RAW piping connections
Tue 7/16/02 1:00 PMWed 7/17/02 8:00 AM32 hrs
Setup rail structure for target & BPM modules
Wed 7/17/02 8:00 AMWed 7/17/02 12:00 PM32 hrs
Install target module in horn box
Thu 7/18/02 7:30 AMThu 7/18/02 11:30 AM32 hrs
Install BPM module, plug in cables
Thu 7/18/02 11:30 AMThu 7/18/02 4:30 PM32 hrs
Install target cooling systems racks
Fri 7/19/02 7:30 AMFri 7/19/02 11:30 AM32 hrs
Install piping, target cooling system to target module
Fri 7/19/02 11:30 AMMon 7/22/02 11:30 AM128 hrs
Remove target cooling piping & BPM cable conn.
Tue 7/23/02 7:30 AMTue 7/23/02 11:30 AM32 hrs
Remove BPM module and Thomson rail structure
Tue 7/23/02 11:30 AMTue 7/23/02 2:30 PM16 hrs
Setup target coffin support structure, coffin
Tue 7/23/02 2:30 PMTue 7/23/02 4:30 PM16 hrs
Remove target module, pulling into coffin
Wed 7/24/02 7:30 AMWed 7/24/02 11:30 AM32 hrs
Remove Coffin and extract target module from coffin
Wed 7/24/02 11:30 AMWed 7/24/02 2:30 PM16 hrs
Setup rail structure for target & BPM modules
Wed 7/24/02 2:30 PMWed 7/24/02 4:30 PM16 hrs
Install target module into horn box
Thu 7/25/02 11:30 AMThu 7/25/02 2:30 PM16 hrs
Install BPM module
Thu 7/25/02 2:30 PMThu 7/25/02 4:30 PM16 hrs
Connect BPM cables, install target cooling piping
Fri 7/26/02 7:30 AMFri 7/26/02 9:30 AM16 hrs
Remove Thomson rail structure, trolley and rails
Fri 7/26/02 9:30 AMFri 7/26/02 11:30 AM16 hrs
Install Striplines
Fri 7/26/02 11:30 AMSat 7/27/02 11:30 AM64 hrs
Install air barrier interface around horn module
Mon 7/29/02 11:00 AMTue 7/30/02 11:00 AM56 hrs
Install triplet quads
Mon 7/29/02 11:00 AMTue 7/30/02 11:00 AM8 hrs
Install Herculite air barrier between rows 4 & 5
Sat 8/3/02 4:00 PMMon 8/5/02 11:00 AM32 hrs
Transport triplet quads and stands to MI-60
Thu 7/11/02 8:00 AMThu 7/11/02 12:00 PM32 hrs
Assemble monitor on target
Mon 7/22/02 11:30 AMMon 7/22/02 4:30 PM8 hrs
Route cables on target module
Thu 7/25/02 7:30 AMThu 7/25/02 11:30 AM8 hrs
Horn Physicists
Sat 7/27/02 11:30 AMMon 7/29/02 11:00 AM31 hrs
Checkout horn cooling system
Sat 7/27/02 11:30 AMSat 7/27/02 2:00 PM3 hrs
Checkout target cooling system
Sat 7/27/02 2:00 PMSat 7/27/02 3:30 PM3 hrs
Checkout Horn Electrical System
Sat 7/27/02 3:30 PMSat 7/27/02 5:00 PM3 hrs
Checkout Target Instrumentation
Sun 7/28/02 8:00 AMSun 7/28/02 9:30 AM3 hrs
Horn on/off test for electrical noise on instrumentation tests
Sun 7/28/02 9:30 AMSun 7/28/02 11:00 AM3 hrs
Horn Pulse Testing
Sun 7/28/02 11:00 AMMon 7/29/02 11:00 AM16 hrs
Riggers
Fri 7/5/02 1:00 PMMon 8/5/02 8:00 PM287.5 hrs
Remove 3 rows of blocks
Tue 7/9/02 3:30 PMTue 7/9/02 9:00 PM27.5 hrs
Install four rows of blocks
Fri 8/2/02 11:00 AMSat 8/3/02 4:00 PM80 hrs
Install two rows of blocks
Mon 8/5/02 11:00 AMMon 8/5/02 8:00 PM40 hrs
Install triplet quads
Mon 7/29/02 11:00 AMMon 7/29/02 8:00 PM40 hrs
Cut off 8" on DS end of trolley rails
Fri 7/5/02 1:00 PMFri 7/5/02 5:00 PM20 hrs
Concrete block cutting
Mon 7/15/02 5:00 PMTue 7/16/02 12:00 PM40 hrs
Setup or cutting
Mon 7/15/02 8:00 AMMon 7/15/02 5:00 PM40 hrs
Electrical techs
Wed 7/10/02 11:00 AMFri 8/2/02 11:00 AM34 hrs
Disconnect triplet Quads
Wed 7/10/02 11:00 AMWed 7/10/02 12:00 PM2 hrs
Connect triplet quads
Wed 7/31/02 11:00 AMFri 8/2/02 11:00 AM32 hrs
RFI
Wed 7/10/02 11:00 AMFri 8/2/02 11:00 AM34 hrs
Disconnect triplet Quads
Wed 7/10/02 11:00 AMWed 7/10/02 12:00 PM2 hrs
Connect triplet quads
Wed 7/31/02 11:00 AMFri 8/2/02 11:00 AM32 hrs
Water Techs
Wed 7/10/02 11:00 AMFri 8/2/02 11:00 AM42 hrs
Disconnect triplet Quads
Wed 7/10/02 11:00 AMWed 7/10/02 12:00 PM2 hrs
Connect triplet quads
Wed 7/31/02 11:00 AMFri 8/2/02 11:00 AM32 hrs
Run drain line from enclosure
Fri 7/12/02 10:00 AMFri 7/12/02 3:00 PM8 hrs
Vacuum Techs
Wed 7/10/02 11:00 AMFri 8/2/02 11:00 AM34 hrs
Disconnect triplet Quads
Wed 7/10/02 11:00 AMWed 7/10/02 12:00 PM2 hrs
Connect triplet quads
Wed 7/31/02 11:00 AMFri 8/2/02 11:00 AM32 hrs
Alignment Group
Wed 7/10/02 8:00 AMWed 7/31/02 12:00 PM141 hrs
"As found" survey of triplet quads
Wed 7/10/02 8:00 AMWed 7/10/02 11:00 AM9 hrs
Align Thomson rail structure in line with horn rails
Wed 7/17/02 1:00 PMWed 7/17/02 5:00 PM12 hrs
Final align triplet quads
Tue 7/30/02 11:00 AMWed 7/31/02 11:00 AM24 hrs
Final Alignment of horn module
Mon 7/15/02 1:00 PMTue 7/16/02 12:00 PM24 hrs
Re-align Thomson rails to horn box
Wed 7/24/02 4:30 PMThu 7/25/02 11:30 AM12 hrs
Align SWIC
Wed 7/31/02 8:00 AMWed 7/31/02 12:00 PM12 hrs
Receiving
Wed 7/10/02 1:00 PMTue 7/23/02 4:30 PM34 hrs
Remove triplet quads
Wed 7/10/02 1:00 PMWed 7/10/02 3:00 PM4 hrs
Install trolley rail system & trolley
Thu 7/11/02 1:00 PMThu 7/11/02 4:00 PM6 hrs
Bring and align coffins
Fri 7/12/02 1:00 PMFri 7/12/02 5:00 PM8 hrs
Setup rail structure for target & BPM modules
Wed 7/17/02 8:00 AMWed 7/17/02 12:00 PM8 hrs
Setup target coffin support structure, coffin
Tue 7/23/02 2:30 PMTue 7/23/02 4:30 PM4 hrs
Transport triplet quads and stands to MI-60
Thu 7/11/02 8:00 AMThu 7/11/02 12:00 PM4 hrs
Operations Group
Thu 6/27/02 1:52 AMMon 8/5/02 10:00 PM315.63 hrs
Search and Secure
Mon 8/5/02 8:00 PMMon 8/5/02 10:00 PM6 hrs
Test Stability and robustness of autotune to dump
Sat 6/29/02 1:52 PMSun 6/30/02 5:52 AM16 hrs
Manual Autotune mode test with offset to dump
Fri 6/28/02 1:52 PMSat 6/29/02 1:52 PM24 hrs
Start Autotune studies to determine offset to dump
Fri 6/28/02 1:52 AMFri 6/28/02 1:52 PM12 hrs
Signal on 5m muon monitor; lower 25m muon monitor
Thu 6/27/02 1:52 PMFri 6/28/02 1:52 AM12 hrs
Target area focussing angle studies with temp. multiwires, short hi intensity tests
Thu 6/27/02 9:52 AMThu 6/27/02 1:52 PM4 hrs
Once Tune established; check out eberm, shielding,intensity monitoring
Thu 6/27/02 1:52 AMThu 6/27/02 9:52 AM8 hrs
Short High Intensity/low rep rate, loss,aperture,emittance studies
Thu 6/27/02 1:52 AMThu 6/27/02 9:52 AM8 hrs
Miscellaneous tuning
Sun 6/30/02 5:52 AMTue 7/9/02 3:30 PM225.63 hrs
Welders
Mon 7/15/02 8:00 AMMon 7/15/02 12:00 PM4 hrs
Add air barrier, angles on horn module
Mon 7/15/02 8:00 AMMon 7/15/02 12:00 PM4 hrs
Safety documentation group
Sat 7/6/02 8:00 AMTue 7/16/02 9:00 AM73 hrs
Full statistics Mars calculations due
Mon 7/8/02 8:00 AMMon 7/8/02 5:00 PM8 hrs
Comment and rewrite period
Mon 7/8/02 8:00 AMWed 7/10/02 5:00 PM24 hrs
Internal exchange of penultimate draft of SA
Sat 7/6/02 8:00 AMSat 7/6/02 5:00 PM8 hrs
Update SAD
Fri 7/12/02 9:00 AMMon 7/15/02 9:00 AM16 hrs
Turn in to SRC
Fri 7/12/02 8:00 AMFri 7/12/02 9:00 AM1 hr
Folder Assembly
Thu 7/11/02 1:00 PMThu 7/11/02 5:00 PM4 hrs
Response from SRC, clearance from BD, docs to 7th floor
Mon 7/15/02 9:00 AMTue 7/16/02 9:00 AM8 hrs
All documents complete
Thu 7/11/02 8:00 AMThu 7/11/02 12:00 PM4 hrs
BD Mech Techs
Mon 7/8/02 8:00 AMTue 7/30/02 5:00 PM864 hrs
Steel installed
Tue 7/9/02 8:00 AMTue 7/9/02 5:00 PM16 hrs
Support structure installed
Mon 7/8/02 8:00 AMMon 7/8/02 5:00 PM16 hrs
Install SWIC
Tue 7/30/02 8:00 AMTue 7/30/02 5:00 PM16 hrs
Joel Misek
Mon 7/15/02 8:00 AMTue 7/16/02 5:00 PM16 hrs
Sketch parts for Dan Snee
Mon 7/15/02 8:00 AMTue 7/16/02 5:00 PM16 hrs
Concrete block cutter
Tue 7/16/02 8:00 AMTue 7/16/02 5:00 PM8 hrs
Concrete block cutting
Tue 7/16/02 8:00 AMTue 7/16/02 5:00 PM8 hrs
Concrete hole driller
Fri 7/12/02 8:00 AMFri 7/12/02 10:00 AM2 hrs
Drill drain hole in enclosure
Fri 7/12/02 8:00 AMFri 7/12/02 10:00 AM2 hrs
Salmon Tariq
Thu 7/11/02 2:00 PMFri 7/12/02 2:00 PM8 hrs
Design Monitor
Thu 7/11/02 2:00 PMFri 7/12/02 2:00 PM8 hrs
Larry Bartoszek
Fri 7/12/02 2:00 PMSat 7/13/02 9:00 AM4 hrs
Model monitor in target model
Fri 7/12/02 2:00 PMSat 7/13/02 9:00 AM4 hrs
BD drafting
Fri 7/12/02 2:00 PMMon 7/15/02 2:00 PM8 hrs
Draft monitor pieces
Fri 7/12/02 2:00 PMMon 7/15/02 2:00 PM8 hrs
WHGF shop
Mon 7/15/02 2:00 PMFri 7/19/02 2:00 PM32 hrs
Fabricate monitor pieces
Mon 7/15/02 2:00 PMFri 7/19/02 2:00 PM32 hrs
Target monitor physicist/EE
Wed 7/17/02 8:00 AMFri 7/19/02 5:00 PM16 hrs
Develop read-out for monitor
Wed 7/17/02 8:00 AMWed 7/17/02 5:00 PM8 hrs
Software integration into controls
Fri 7/19/02 8:00 AMFri 7/19/02 5:00 PM8 hrs
Electricians
Wed 7/17/02 1:00 PMMon 7/22/02 12:00 PM40 hrs
Pull cables in MI-12
Thu 7/18/02 8:00 AMThu 7/18/02 5:00 PM8 hrs
Install electr. boxes for target cooling, pull & connect cables
Wed 7/17/02 1:00 PMMon 7/22/02 12:00 PM32 hrs