Project Start Date: Tue 6/25/02 8:00 AM
Project Finish Date: Mon 8/5/02 10:00 PM
| ID | Task_Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
|---|---|---|---|---|---|---|
| 1 | Beam Commissioning Tasks | 34 d | Thu 6/27/02 1:52 AM | Mon 8/5/02 10:00 PM | ||
| 2 | Phase II beam run | 10.81 d | Thu 6/27/02 1:52 AM | Tue 7/9/02 3:30 PM | ||
| 3 | Short High Intensity/low rep rate, loss,aperture,emittance studies | 1 d | Thu 6/27/02 1:52 AM | Thu 6/27/02 9:52 AM | Operations Group | |
| 4 | Once Tune established; check out eberm, shielding,intensity monitoring | 1 d | Thu 6/27/02 1:52 AM | Thu 6/27/02 9:52 AM | 3SS | Operations Group |
| 5 | Target area focussing angle studies with temp. multiwires, short hi intensity tests | 0.5 d | Thu 6/27/02 9:52 AM | Thu 6/27/02 1:52 PM | 4 | Operations Group |
| 6 | Signal on 5m muon monitor; lower 25m muon monitor | 1.5 d | Thu 6/27/02 1:52 PM | Fri 6/28/02 1:52 AM | 5 | Operations Group |
| 7 | Start Autotune studies to determine offset to dump | 1.5 d | Fri 6/28/02 1:52 AM | Fri 6/28/02 1:52 PM | 6 | Operations Group |
| 8 | Manual Autotune mode test with offset to dump | 3 d | Fri 6/28/02 1:52 PM | Sat 6/29/02 1:52 PM | 7 | Operations Group |
| 9 | Test Stability and robustness of autotune to dump | 2 d | Sat 6/29/02 1:52 PM | Sun 6/30/02 5:52 AM | 8 | Operations Group |
| 10 | Miscellaneous tuning | 26.2 d | Sun 6/30/02 5:52 AM | Tue 7/9/02 3:30 PM | 9 | Operations Group |
| 11 | Safety Documentation Milestones | 15 d | Sat 7/6/02 8:00 AM | Tue 7/23/02 5:00 PM | ||
| 12 | Internal exchange of penultimate draft of SA | 1 d | Sat 7/6/02 8:00 AM | Sat 7/6/02 5:00 PM | Safety documentation group | |
| 13 | Comment and rewrite period | 3 d | Mon 7/8/02 8:00 AM | Wed 7/10/02 5:00 PM | 12 | Safety documentation group |
| 14 | Full statistics Mars calculations due | 1 d | Mon 7/8/02 8:00 AM | Mon 7/8/02 5:00 PM | Safety documentation group | |
| 15 | All documents complete | 0.5 d | Thu 7/11/02 8:00 AM | Thu 7/11/02 12:00 PM | 14,13 | Safety documentation group |
| 16 | Folder Assembly | 0.5 d | Thu 7/11/02 1:00 PM | Thu 7/11/02 5:00 PM | 15 | Safety documentation group |
| 17 | Turn in to SRC | 0.13 d | Fri 7/12/02 8:00 AM | Fri 7/12/02 9:00 AM | 16 | Safety documentation group |
| 18 | Update SAD | 2 d | Fri 7/12/02 9:00 AM | Mon 7/15/02 9:00 AM | 17 | Safety documentation group |
| 19 | Response from SRC, clearance from BD, docs to 7th floor | 1 d | Mon 7/15/02 9:00 AM | Tue 7/16/02 9:00 AM | 18 | Safety documentation group |
| 20 | Approval process complete | 0 d | Tue 7/23/02 5:00 PM | Tue 7/23/02 5:00 PM | 19 | |
| 21 | Joel's Parallel tasks | 21.5 d | Fri 7/5/02 5:00 PM | Wed 7/31/02 12:00 PM | ||
| 22 | LMC Shielding Installation | 3 d | Fri 7/5/02 5:00 PM | Tue 7/9/02 5:00 PM | ||
| 23 | Steel and Support Structure ready | 0 d | Fri 7/5/02 5:00 PM | Fri 7/5/02 5:00 PM | ||
| 24 | Support structure installed | 1 d | Mon 7/8/02 8:00 AM | Mon 7/8/02 5:00 PM | 23 | BD Mech Techs[200%] |
| 25 | Steel installed | 1 d | Tue 7/9/02 8:00 AM | Tue 7/9/02 5:00 PM | 24 | BD Mech Techs[200%] |
| 26 | Install Bayonet SWIC in beamline | 1.5 d | Tue 7/30/02 8:00 AM | Wed 7/31/02 12:00 PM | ||
| 27 | Install SWIC | 1 d | Tue 7/30/02 8:00 AM | Tue 7/30/02 5:00 PM | BD Mech Techs[200%] | |
| 28 | Align SWIC | 0.5 d | Wed 7/31/02 8:00 AM | Wed 7/31/02 12:00 PM | 27 | Alignment Group[300%] |
| 29 | Fabrication of horn box air dam interface pieces | 7 d | Mon 7/15/02 8:00 AM | Mon 7/22/02 5:00 PM | ||
| 30 | Sketch parts for Dan Snee | 2 d | Mon 7/15/02 8:00 AM | Tue 7/16/02 5:00 PM | 62 | Joel Misek |
| 31 | Make interface sheets | 1 wk | Wed 7/17/02 8:00 AM | Mon 7/22/02 5:00 PM | 30 | |
| 32 | 25m Enclosure De-watering | 0.75 d | Fri 7/12/02 8:00 AM | Fri 7/12/02 3:00 PM | ||
| 33 | Drill drain hole in enclosure | 0.25 d | Fri 7/12/02 8:00 AM | Fri 7/12/02 10:00 AM | 56 | Concrete hole driller |
| 34 | Run drain line from enclosure | 0.5 d | Fri 7/12/02 10:00 AM | Fri 7/12/02 3:00 PM | 33 | Water Techs[200%] |
| 35 | Air Handling Equipment Installation | 10 d | Mon 7/8/02 8:00 AM | Thu 7/18/02 5:00 PM | ||
| 36 | Hardware installed--check with Lee Hammond | 1 wk | Mon 7/8/02 8:00 AM | Fri 7/12/02 5:00 PM | ||
| 37 | Hardware wired and tested | 1 wk | Sat 7/13/02 8:00 AM | Thu 7/18/02 5:00 PM | 36 | |
| 38 | Concrete Shielding Block cutting | 2 d | Mon 7/15/02 8:00 AM | Tue 7/16/02 5:00 PM | ||
| 39 | Setup or cutting | 1 d | Mon 7/15/02 8:00 AM | Mon 7/15/02 5:00 PM | Riggers[500%] | |
| 40 | Concrete block cutting | 1.5 d | Mon 7/15/02 5:00 PM | Tue 7/16/02 5:00 PM | 39 | Riggers[500%],Concrete block cutter |
| 41 | New Target Beam Monitor | 11.81 d | Thu 7/11/02 2:00 PM | Thu 7/25/02 11:30 AM | ||
| 42 | Design Monitor | 1 d | Thu 7/11/02 2:00 PM | Fri 7/12/02 2:00 PM | Salmon Tariq | |
| 43 | Model monitor in target model | 0.5 d | Fri 7/12/02 2:00 PM | Sat 7/13/02 9:00 AM | 42 | Larry Bartoszek |
| 44 | Draft monitor pieces | 1 d | Fri 7/12/02 2:00 PM | Mon 7/15/02 2:00 PM | 42 | BD drafting |
| 45 | Fabricate monitor pieces | 4 d | Mon 7/15/02 2:00 PM | Fri 7/19/02 2:00 PM | 44 | WHGF shop |
| 46 | Assemble monitor on target | 0.5 d | Mon 7/22/02 11:30 AM | Mon 7/22/02 4:30 PM | 45 | Hiep's Group[200%] |
| 47 | Route cables on target module | 0.5 d | Thu 7/25/02 7:30 AM | Thu 7/25/02 11:30 AM | 46 | Hiep's Group[200%] |
| 48 | Develop read-out for monitor | 1 d | Wed 7/17/02 8:00 AM | Wed 7/17/02 5:00 PM | Target monitor physicist/EE | |
| 49 | Pull cables in MI-12 | 1 d | Thu 7/18/02 8:00 AM | Thu 7/18/02 5:00 PM | 48 | Electricians |
| 50 | Software integration into controls | 1 d | Fri 7/19/02 8:00 AM | Fri 7/19/02 5:00 PM | 49 | Target monitor physicist/EE |
| 51 | Monitor ready for phase III | 0 d | Thu 7/25/02 11:30 AM | Thu 7/25/02 11:30 AM | 50,47 | |
| 52 | Install Horn & Stripline & Hot Horn Test | 14 d | Fri 7/5/02 1:00 PM | Mon 7/22/02 12:00 PM | ||
| 53 | Remove 3 rows of blocks | 0.69 d | Tue 7/9/02 3:30 PM | Tue 7/9/02 9:00 PM | 10 | Riggers[500%] |
| 54 | "As found" survey of triplet quads | 0.38 d | Wed 7/10/02 8:00 AM | Wed 7/10/02 11:00 AM | 53 | Alignment Group[300%] |
| 55 | Disconnect triplet Quads | 0.13 d | Wed 7/10/02 11:00 AM | Wed 7/10/02 12:00 PM | 54 | Electrical techs[200%],RFI[200%],Water Techs[200%],Vacuum Techs[200%] |
| 56 | Remove triplet quads | 0.25 d | Wed 7/10/02 1:00 PM | Wed 7/10/02 3:00 PM | 55 | Hiep's Group[800%],Receiving[200%] |
| 57 | Remove BPMs and multiwires in horn cavity | 0.19 d | Wed 7/10/02 3:00 PM | Wed 7/10/02 4:30 PM | 56 | Hiep's Group[800%] |
| 58 | Transport triplet quads and stands to MI-60 | 0.5 d | Thu 7/11/02 8:00 AM | Thu 7/11/02 12:00 PM | 57 | Hiep's Group[800%],Receiving |
| 59 | Cut off 8" on DS end of trolley rails | 0.5 d | Fri 7/5/02 1:00 PM | Fri 7/5/02 5:00 PM | Riggers[500%] | |
| 60 | Install trolley rail system & trolley | 0.38 d | Thu 7/11/02 1:00 PM | Thu 7/11/02 4:00 PM | 59,58 | Hiep's Group[800%],Receiving[200%] |
| 61 | Bring and align coffins | 0.56 d | Fri 7/12/02 1:00 PM | Sat 7/13/02 8:00 AM | 60 | Hiep's Group[800%],Receiving[200%] |
| 62 | Install horn module & remove coffins | 1 d | Sat 7/13/02 8:00 AM | Mon 7/15/02 8:00 AM | 61,34 | Hiep's Group[800%] |
| 63 | Add air barrier, angles on horn module | 0.5 d | Mon 7/15/02 8:00 AM | Mon 7/15/02 12:00 PM | 62 | Hiep's Group[800%],Welders |
| 64 | Final Alignment of horn module | 1 d | Mon 7/15/02 1:00 PM | Tue 7/16/02 12:00 PM | 63 | Alignment Group[300%] |
| 65 | Install RAW piping connections | 0.5 d | Tue 7/16/02 1:00 PM | Wed 7/17/02 8:00 AM | 64 | Hiep's Group[800%] |
| 66 | Setup rail structure for target & BPM modules | 0.5 d | Wed 7/17/02 8:00 AM | Wed 7/17/02 12:00 PM | 65 | Hiep's Group[800%],Receiving[200%] |
| 67 | Align Thomson rail structure in line with horn rails | 0.5 d | Wed 7/17/02 1:00 PM | Wed 7/17/02 5:00 PM | 66 | Alignment Group[300%] |
| 68 | Install target module in horn box | 0.5 d | Thu 7/18/02 7:30 AM | Thu 7/18/02 11:30 AM | 67 | Hiep's Group[800%] |
| 69 | Install BPM module, plug in cables | 0.5 d | Thu 7/18/02 11:30 AM | Thu 7/18/02 4:30 PM | 68 | Hiep's Group[800%] |
| 70 | Install target cooling systems racks | 0.5 d | Fri 7/19/02 7:30 AM | Fri 7/19/02 11:30 AM | 69 | Hiep's Group[800%] |
| 71 | Install piping, target cooling system to target module | 2 d | Fri 7/19/02 11:30 AM | Mon 7/22/02 11:30 AM | 70 | Hiep's Group[800%] |
| 72 | Install electr. boxes for target cooling, pull & connect cables | 4 d | Wed 7/17/02 1:00 PM | Mon 7/22/02 12:00 PM | 67SS | Electricians |
| 73 | Begin Hot Target Handling dry run | 4.44 d | Tue 7/23/02 7:30 AM | Sat 7/27/02 11:30 AM | ||
| 74 | Remove target cooling piping & BPM cable conn. | 0.5 d | Tue 7/23/02 7:30 AM | Tue 7/23/02 11:30 AM | 72 | Hiep's Group[800%] |
| 75 | Remove BPM module and Thomson rail structure | 0.25 d | Tue 7/23/02 11:30 AM | Tue 7/23/02 2:30 PM | 74 | Hiep's Group[800%] |
| 76 | Setup target coffin support structure, coffin | 0.25 d | Tue 7/23/02 2:30 PM | Tue 7/23/02 4:30 PM | 75 | Hiep's Group[800%],Receiving[200%] |
| 77 | Remove target module, pulling into coffin | 0.5 d | Wed 7/24/02 7:30 AM | Wed 7/24/02 11:30 AM | 76 | Hiep's Group[800%] |
| 78 | Remove Coffin and extract target module from coffin | 0.25 d | Wed 7/24/02 11:30 AM | Wed 7/24/02 2:30 PM | 77 | Hiep's Group[800%] |
| 79 | Setup rail structure for target & BPM modules | 0.25 d | Wed 7/24/02 2:30 PM | Wed 7/24/02 4:30 PM | 78 | Hiep's Group[800%] |
| 80 | Re-align Thomson rails to horn box | 0.5 d | Wed 7/24/02 4:30 PM | Thu 7/25/02 11:30 AM | 79 | Alignment Group[300%] |
| 81 | Install target module into horn box | 0.25 d | Thu 7/25/02 11:30 AM | Thu 7/25/02 2:30 PM | 80,47 | Hiep's Group[800%] |
| 82 | Install BPM module | 0.25 d | Thu 7/25/02 2:30 PM | Thu 7/25/02 4:30 PM | 81 | Hiep's Group[800%] |
| 83 | Connect BPM cables, install target cooling piping | 0.25 d | Fri 7/26/02 7:30 AM | Fri 7/26/02 9:30 AM | 82 | Hiep's Group[800%] |
| 84 | Remove Thomson rail structure, trolley and rails | 0.25 d | Fri 7/26/02 9:30 AM | Fri 7/26/02 11:30 AM | 83 | Hiep's Group[800%] |
| 85 | Install Striplines | 1 d | Fri 7/26/02 11:30 AM | Sat 7/27/02 11:30 AM | 84 | Hiep's Group[800%] |
| 86 | Horn & target testing | 0.94 d | Sat 7/27/02 11:30 AM | Mon 7/29/02 11:00 AM | ||
| 87 | Checkout horn cooling system | 0.19 d | Sat 7/27/02 11:30 AM | Sat 7/27/02 2:00 PM | 85 | Horn Physicists[200%] |
| 88 | Checkout target cooling system | 0.19 d | Sat 7/27/02 2:00 PM | Sat 7/27/02 3:30 PM | 87 | Horn Physicists[200%] |
| 89 | Checkout Horn Electrical System | 0.19 d | Sat 7/27/02 3:30 PM | Sat 7/27/02 5:00 PM | 88 | Horn Physicists[200%] |
| 90 | Checkout Target Instrumentation | 0.19 d | Sun 7/28/02 8:00 AM | Sun 7/28/02 9:30 AM | 89 | Horn Physicists[200%] |
| 91 | Horn on/off test for electrical noise on instrumentation tests | 0.19 d | Sun 7/28/02 9:30 AM | Sun 7/28/02 11:00 AM | 90 | Horn Physicists[200%] |
| 92 | Horn Pulse Testing | 1 d | Sun 7/28/02 11:00 AM | Mon 7/29/02 11:00 AM | 91 | Horn Physicists[200%] |
| 93 | Final Installation | 6.63 d | Mon 7/29/02 11:00 AM | Mon 8/5/02 10:00 PM | ||
| 94 | Install air barrier interface around horn module | 1 d | Mon 7/29/02 11:00 AM | Tue 7/30/02 11:00 AM | 92,31 | Hiep's Group[700%] |
| 95 | Install triplet quads | 1.44 d | Mon 7/29/02 11:00 AM | Tue 7/30/02 11:00 AM | 92 | Hiep's Group,Riggers[500%] |
| 96 | Final align triplet quads | 1 d | Tue 7/30/02 11:00 AM | Wed 7/31/02 11:00 AM | 95 | Alignment Group[300%] |
| 97 | Connect triplet quads | 2 d | Wed 7/31/02 11:00 AM | Fri 8/2/02 11:00 AM | 96 | RFI[200%],Vacuum Techs[200%],Electrical techs[200%],Water Techs[200%] |
| 98 | Install four rows of blocks | 2 d | Fri 8/2/02 11:00 AM | Sat 8/3/02 4:00 PM | 97,40 | Riggers[500%] |
| 99 | Install Herculite air barrier between rows 4 & 5 | 0.5 d | Sat 8/3/02 4:00 PM | Mon 8/5/02 11:00 AM | 98 | Hiep's Group[800%] |
| 100 | Install two rows of blocks | 1 d | Mon 8/5/02 11:00 AM | Mon 8/5/02 8:00 PM | 99 | Riggers[500%] |
| 101 | Search and Secure | 0.25 d | Mon 8/5/02 8:00 PM | Mon 8/5/02 10:00 PM | 100 | Operations Group[300%] |
| 102 | Ready for beam Phase III | 0 d | Mon 8/5/02 10:00 PM | Mon 8/5/02 10:00 PM | 101,20,37,28,25 |